In a briefing, the National Grid Corp. of the Philippines (NGCP) said the overall transmission charges inched up to P1.3504 per kilowatt hour (kWh) from the P1.2583 in the December 2024 billing ...
MANILA, Philippines — The National Grid Corp. of the Philippines (NGCP) has secured approval from the Energy Regulatory Commission (ERC) to implement four transmission projects worth over P5 ...
NGCP’s proposed Sumangga 138-kV substation project, which must be completed on or before March 31, 2028, aims to address overloading in the existing Ormoc-Baybay 69 kV line.
The National Grid Corporation of the Philippines (NGCP) on Wednesday announced that its transmission charges will increase this month, which would affect the bills of power grid consumers across the ...
NGCP business and regulatory development head Julius Ryan Datingaling said in a press conference yesterday that the overall transmission charge went up to P1.3504 per kilowatt-hour from P1.2583 ...
THE Energy Regulatory Commission (ERC) on Feb. 12 announced the approval of four projects of the National Grid Corp. of the Philippines (NGCP) aimed to boost stability in the country's electricity ...
THE Energy Regulatory Commission (ERC) has approved four proposed transmission projects of the National Grid Corp. of the Philippines (NGCP) worth a combined P5.02 billion. The approved projects are ...
NGCP said AS rates in the January 2025 billing period increased 12 percent to P0.6640 per kilowatt-hour (kWh) from P0.5928 per kWh in the December 2024 billing period. The increase was due to the ...
The Energy Regulatory Commission (ERC) approved four transmission projects of National Grid Corp. of the Philippines (NGCP) estimated to cost P5 billion. The ERC, in its notice of commission action, ...
Some results have been hidden because they may be inaccessible to you
Show inaccessible results